Infrastructure | 20 June 2012
Two mega projects ready for take-off
JNPT CT-4 & DFCC Western Corridor: expect
project awards of USD5b-7b in FY13/14
INFRASTRUCTURE: Multiplier Effect
JNPT's CT-4 and DFCC Western
JNPT has selected the Port Authority of Singapore to
construct and operate its fourth container terminal (CT-
4), which will nearly double existing capacity.
JNPT's CT-4 expansion is contingent on DFCC for evacuation
and the viability of DFCC's Western Corridor is contingent
on JNPT expansion, as containers will account for 75-80%
of traffic.
We expect project awards of USD5b-7b in FY13/14 and
prefer L&T to play the theme.
corridor are high "multiplier effect"
projects, with interlinked viability
Both projects targeted to be
commissioned by FY16/17
Expect USD5-7b worth of
project awards in FY13/14
Successful implementation to lead
to a chain of benefits across sectors,
boosting the investment cycle
Ray of Hope
will highlight the bright spots in an otherwise
bleak scenario in the economy or any sector or company.
JNPT's expansion plans to nearly double capacity:
The
Jawaharlal Nehru Port Trust (JNPT) has selected (in
September 2011) the consortium led by Port Authority
of Singapore to construct and operate its fourth
container terminal (CT-4). JNPT currently has a capacity
of 4.1m TEUs and CT-4 will add a further 4.8m TEUs. The
concession agreement is expected to be signed shortly.
Phase-1 of CT-4 (2.4m TEUs) is likely to be completed by
2015/16 at an estimated cost of ~INR38b.
CT-4 / Western Corridor project viability interlinked:
JNPT's CT-4 operations are strongly interlinked with
Dedicated Freight Corridor Corporation's (DFCC)
Western Corridor project, given the constraints in terms
of railway capacity. The Railways account for ~27% of
the hinterland transport for JNPT and the existing
network is congested, with limited room for expansion.
Hence, the near doubling of container capacity post
commissioning of CT-4 is largely dependent on DFCC
for evacuation. The economic viability of DFCC's
Western Corridor project is also linked to JNPT
expansion, as containers will account for 75-80% of
traffic. Land acquisition in the JNPT-Vadodara section
has been significantly behind schedule (near nil land
acquired around Mumbai, Surat), while the Vadodara-
Rewari section has witnessed 83% land acquisition.
Expect project awards of USD5b-7b in FY13/14:
We
expect substantial parts of the project awards for both
CT-4 (INR38b, phase-1) and DFCC Western Corridor
(~USD8b) to be completed in FY13/14. This will entail
interesting opportunities for construction players. Both
the projects are expected to be commissioned by FY16/
17. We believe that DFCC could provide a 'multiplier
effect' for India in many ways, and successful
implementation will lead to several benefits.
How to play the theme - L&T is the best bet:
We believe
L&T (Buy) will be a clear beneficiary of the project
awards of USD5b-7b expected in FY13/14 for CT-4 and
the Western Corridor. L&T is also one of the two
consortiums pre-qualified to submit price bids in two
packages of the Western Corridor (size ~USD1b). Adani
Port (Not Rated) will also be a beneficiary of the shift
in the northern hinterland container cargo from
Maharashtra to Gujarat - JNPT's capacity is largely
saturated till CT-4 / western DFCC becomes operational
and the recent TAMP (Tariff Authority on Major Ports)
tariff reduction for private operators at JNPT will lead
them to lower volumes, as efficiency gets punished.
Adani Port already accounts for ~25% of the western
region container traffic and the transition is expected
to be rather quick over the next 3-4 years.
Satyam Agarwal
(AgarwalS@MotilalOswal.com); +91 22 39820 5410
Nalin Bhatt
(NalinBhatt@MotilalOswal.com) /
Pooja Kachhawa
(Pooja.Kachhawa@MotilalOswal.com)
1

Ray of Hope
| Infrastructure
JNPT, India's most profitable port, doubling capacity
Expect meaningful project awards in FY13
We met the management of
Jawaharlal Nehru Port Trust
(JNPT).
JNPT has a market share of
56% in India's container
cargo. JNPT has three
container terminals - two
run by private parties (DP
World and APM Terminal /
Concor) and one by the port
trust. This gives JNPT a strong
landloard-like character. Its
total handling capacity
stands at 4.1m TEUs per
annum, while throughput
was 4.32m TEUs in FY12.
Roads represent the largest
share
in
hinterland
transport at 73%, while
railways contribute ~27%.
JNPT is the most profitable
port trust in the country, with
FY11 PAT at INR5.4b and net
cash balance of INR17.3b.
This is largely due to its
landlord-like character,
which gives it steady royalty
income from BOT operators
(accounts for 55-60% of the
charges at the port) and also
vessel-related charges.
JNPT currently has three container terminals with a total capacity of 4.1m TEUs per annum.
It is adding a fourth terminal (CT-4), which will have a capacity of 4.8m TEUs per annum.
The total project cost is INR67b and we expect awards for phase-1 to commence in FY13.
JNPT, India's largest container handling port…
Commissioned on 26 May 1989, Jawaharlal Nehru Port Trust (JNPT) is India's largest
container handling port, with a market share of 56% in India's container cargo. It has
three container terminals - two run by private parties (DP World and APM Terminal /
Concor) and one by the port trust. This gives JNPT a strong landloard-like character. Its
total handling capacity stands at 4.1m TEUs per annum, while throughput was 4.32m
TEUs in FY12, translating into 100% capacity utilization. Roads represent the largest
share in hinterland transport at 73%, while railways contribute ~27%.
…and the most profitable port in the country…
JNPT is the most profitable port trust in the country, with FY11 PAT at INR5.4b and net
cash balance of INR17.3b. This is largely due to its landlord-like character, which gives
it steady royalty income from BOT operators (accounts for 55-60% of the charges at
the port) and also vessel-related charges.
…has mega expansion plans to double capacity
JNPT has selected (in September 2011) the consortium led by Port Authority of
Singapore to construct and operate its fourth container terminal (CT-4). JNPT currently
has a capacity of 4.1m TEUs and CT-4 will add a further 4.8m TEUs. Quoted revenue
share stands at 50.8%, which is the highest in any bid. The concession agreement is
expected to be signed shortly. Recently, ABG has walked out of the contract and PSA
International, Singapore will be the sole member of the consortium.
Expect meaningful project awards in FY13
CT-4 will be executed in two phases; phase-1 (2.4m TEUs) is likely to be completed by
2015/16 at an estimated cost of ~INR38b. Phase-2, estimated to cost INR28b, is expected
to be completed within eight years from the signing of the concession agreement.
The total project cost is INR67b and we expect project awards for phase-1 to commence
in FY13.
JNPT: CT-4 entails a revenue sharing of 50.8%
Phase I
*Phase II
Quay Length (Mtrs)
1000
1000
Draft (Mtrs)
14
14
Capacity (In Million TEUs)
2.4
2.4
Developer/Operators
PSA (76%) & ABG (24%) #
-
Revenue sharing (%)
50.8
Concession period (yrs)
30
Project cost (INR b)
38
28
* Phase-2 shall be commenced when annual throughput of phase-1 reaches 1m TEUs or
within 6 years from the signing of concession agreement, whichever is earlier.
# Project was initially awarded to a consortium of PSA, Singapore and ABG; in April 2012, the
consortium members informed JNPT that PSA, Singapore alone will take the project.
2
The total project cost for
CT-4 is INR67b and we
expect awards for phase-
1 to commence in FY13
20 June 2012

Ray of Hope
| Infrastructure
JNPT has recently opened the price bids for the dredging contract (to deepen the
channel from 11.5 meters to 14 meters). Post completion, the port can accommodate
vessels upto 6,000 TEUs v/s 3,000/4,000 TEUs currently, which will be a big efficiency
booster for the trade, given lower transshipment requirements. Royal Boskalis
Westminster NV Dredging is the lowest bidder at INR12.2b and the contract is likely to
be awarded shortly. We further understand that while the IRR of the project is
estimated at 15-16%, the economic return including the savings to the trade is
estimated at ~40%. This dredging contract award is an important milestone for the CT-
4 expansion.
JNPT: Layout plan
The total handling capacity of the current three container terminals is 4.1m TEUs per annum.
CT-4 will add 4.8m TEUs, more than doubling the existing capacity.
JNPT: Existing container terminal facilities
JNPT has a strong
landlord-like character;
two of its three container
facilities are with private
operators.
JNPCT
NSICT
GTICT
Quay Length (Mtrs)
680
600
712
Draft (Mtrs)
12.5
12.5
12.5
Capacity (In Million TEUs)
1.1
1.2
1.8
Throughput (in Million TEUs) - FY12
1.0
1.4
1.9
Capacity Utilization %
94
117
106
Revenue sharing
na
Fixed Royalty
35.5%
JNPTC: Operated by JNPT
NSICT: Operated by DP World and is India's first privately managed container terminal
GTICT: Operated by APM Terminals (74%) and Concor (26%)
TOTAL
1,992
--
4.1
4.3
105
20 June 2012
3

Ray of Hope
| Infrastructure
JNPT: Robust financials, given landlord-like character
Revenue composition
Financial matrix (INR m)
Capital Employed
Total assets
Current assets
Current liabilities
Net Profit
ROCE (%)
FY10
18,250
44,477
15,120
7,823
5,413
34.4
FY11
18,710
52,057
17,372
9,892
5,435
33.8
JNPT is the most profitable port trust in the country, with FY11 PAT at INR5.4b and net cash balance of INR17.3b.
This is largely due to its landlord-like character, which gives it steady royalty income from BOT operators
(accounts for 55-60% of the charges at the port) and also vessel-related charges.
Source: JNPT, MOSL
JNPT: One of the largest ports in India
Capacity of major ports in India (m tons)
Capacity of minor ports in India (m tons)
Source: Industry, IPA
20 June 2012
4

Ray of Hope
| Infrastructure
CT-4 / DFCC Western Corridor project viability interlinked
Expect project awards of USD5b-7b in FY13/14; plus multiplier benefits
While JNPT's CT-4 will rely on DFCC's Western Corridor for cargo evacuation, viability of the
latter will depend on cargo traffic from the former.
We expect substantial parts of the project awards for both CT-4 (INR38b, phase-1) and
DFCC Western Corridor (~USD8b) to be completed in FY13/14.
Both the projects are expected to be commissioned by FY16/17 and will lead to multiplier
benefits for the trade.
Viability of JNPT's CT-4 and DFCC's Western Corridor interlinked
The Railways account for
~27% of the hinterland
transport for JNPT and
the existing network is
congested, with limited
room for expansion
JNPT's CT-4 operations are strongly interlinked with Dedicated Freight Corridor
Corporation's (DFCC) Western Corridor project, given the constraints in terms of railway
capacity. The Railways account for ~27% of the hinterland transport for JNPT and the
existing network is congested, with limited room for expansion. Hence, the near
doubling of container capacity post commissioning of CT-4 is largely dependent on
DFCC for evacuation. The economic viability of DFCC's Western Corridor project is also
linked to JNPT expansion, as containers will account for 75-80% of traffic.
Expect project awards of USD5b-7b in FY13/14
We expect substantial parts of the project awards for both CT-4 (INR38b, phase-1) and
DFCC Western Corridor (~USD8b) to be completed in FY13/14. This will entail interesting
opportunities for construction players. Both the projects are expected to be
commissioned by FY16/17. We believe that DFCC could provide a 'multiplier effect' for
India in many ways, and successful implementation will lead to several benefits.
There are challenges, too
There has
been no progress
in land acquisition near
the Mumbai/Thane belt,
given environmental
issues
DFCC's Western Corridor project is being contemplated in three phases: Vadodara to
Rewari (920km), JNPT to Vadodara (430km), and Rewari to Dadri (140km). While land
acquisition for the Vadodara-Rewari section has been completed to the extent of
83%, land acquisition for the JNPT-Vadadara section is lagging. There has been no
progress in land acquisition near the Mumbai/Thane belt, given environmental issues
like forest land in Thane, right of passage through Sanjay Gandhi National Park, etc.
Even in locations like Surat, just 1.3% of the land required has been acquired.
Delayed implementation of the Western Corridor (JNPT-Vadodara section) will be a
setback for JNPT's CT-4, while minor ports in Gujarat (Mundra / Hazira / Pipavav) will
be the key beneficiaries. The government of Maharashtra is trying to expedite the
land acquisition.
20 June 2012
5

Ray of Hope
| Infrastructure
Western Dedicated Freight Corridor: Route map
The Vadodra-Rewari
section is expected to be
completed by 2016/17;
however, the JNPT-
Vadodara could be
delayed due to land
acquisition issues
Western Dedicated Freight Corridor: Land acquisition status
Total Scope
kms Area (Ha)
274
1,064
359
958
196
907
75
558
27
122
930
3,608
202
460
118
239
108
612
141
942
569
2,252
1,499
5,860
20A
kms Area (Ha)
274
1,064
359
958
144
721
75
552
27
122
930
3,608
202
460
118
239
108
612
141
942
569
2252
1,499
5,860
kms
274
339
80
75
23
826
59
95
108
52
464
1,290
20E
Area (Ha)
1,064
924
459
412
82
3,205
77
148
446
307
1718
4,923
kms
274
339
78
73
0
776
0
4
108
0
143
919
20F
Area (Ha)
1,064
924
411
386
0
2,998
0
3
362
0
782
3,780
Progress Compensation (INR M)
(%)
Award
Disbursed
100.0
1,960
1,370
96.5
1,450
770
45.3
820
130
69.2
3,550
3,280
0.0
0
0
83.1
7,780
5,550
0.0
0
0
1.3
73
44
59.2
3,590
3,400
0.0
0
0
34.7
3,663
3,444
64.5
22,886
1,370
Jaipur
Ajmer
Ahmedabad
Vadodara
Dadri
Total Phase 1
Mumbai
Surat
Vadodara
Dadri
Total Phase 2
Grand Total
While land acquisition for the Vadodara-Rewari section has been completed to the extent of 83%,
land acquisition for the JNPT-Vadadara section is lagging significantly
20 June 2012
6

Ray of Hope
| Infrastructure
PPP in ports - a good beginning
Will the momentum sustain?
Given the poor finances of port trusts, expansion projects at major ports need to be carried
out through the public private partnership (PPP) route.
As at March 2012, PPP projects of INR94b (205m tons) at major ports have been completed,
while projects worth INR183b (185m tons) are under implementation. Projects under
bidding stand at INR158b (158m tons).
While the initial progress has been noteworthy, there has been a meaningful slowdown in
terms of PPP projects being awarded at major ports over the last 18 months.
Meaningful slowdown in PPP project awards at major ports
As at March 2012, PPP
projects of INR94b (205m
tons) at major ports have
been completed
As at March 2012, PPP projects of INR94b (205m tons) at major ports have been
completed, while projects worth INR183b (185m tons) are under implementation.
Projects under bidding stand at INR91b (158m tons). While the initial progress has
been noteworthy, there has been a meaningful slowdown in terms of PPP projects
being awarded at major ports over the last 18 months.
PPP projects at major ports
Completed
Under Implementation
Under Bidding
INR B
94.4
183.5
90.6
M tons
205
185
158
The key issues plaguing the sector are:
Delays in getting clearances:
In the recent past, projects awarded on PPP basis
have been delayed due to the time taken to obtain environmental and other
clearances. As in most other sectors, environmental clearances for port projects
are obtained post project award.
Strained finances, poor draft:
Several existing ports like Mumbai, Chennai, Kolkata,
etc were commissioned over 100 years ago, and the existing draft is a hindrance.
Corrective action entails massive dredging, which is capital intensive, and in several
instances, the port trusts do not have sufficient finances. Globally, part of the
dredging costs is shared by the government, but this is not the case in India.
Regulated tariff by Tariff Authority for Major Ports (TAMP):
The TAMP return
framework is not incentivizing efficiency (16% RoCE). Higher throughput than the
minimum committed capacity actually leads to lower RoCE in several instances.
Several existing ports like
Mumbai, Chennai,
Kolkata, etc were
commissioned over 100
years ago, and the
existing draft is a
hindrance
Case Study: TAMP asks NSICT/GTICT to cut tariffs, punishing efficiency
TAMP regime
punishes efficiency
In February 2012, TAMP ordered Nhava Sheva International Container Terminal (NSICT)
and Gateway Terminal (GTICT) to lower tariffs by 27.85% and 44.28%, respectively.
The tariff cut was largely because these ports were operating at 117%/135% capacity
utilization (based on the minimum guaranteed throughput). This tantamounts to
punishing efficiency, as the revenue share (paid to JNPT) is not allowed as cost while
fixing the tariff. So, while the tariffs are based on actual throughput, the port operator
faces lower returns, as it has to pay the revenue share out of the reduced RoCE year
on year. Hence, the operators will attempt to lower their throughput to just the
minimum guaranteed.
7
20 June 2012

Ray of Hope
| Infrastructure
Private operators at JNPT to lower volumes, as efficiency gets punished
Minimum Guaranteed
Throughput
1.2
1.4
Actual Throughput (FY12)
1.4
1.9
Capacity Utilization (%)
117
135
Source: Company, MOSL
NSICT
GTICT
Projects under implementation stage
Sr.
No
1
Project Name
Capacity Est. Cost Structure
(m tons)
INR b
2.0
1.9
10.2
6.0
6.7
1.1 BOT
0.6 BOT
4.4 BOT
3.2 BOT
3.1 BOT
Award
2
3
4
5
6
7
8
9
10
Visakhapatnam port
Development of Western quay(WQ-6) in the northern arm of
Inner harbour of VPT for handling Dry bulk cargo at Vizag
Development of EQ-10 berth in Inner Harbour for handling liquid cargo at Vizag
Mechanised Coal handling facilities at General cum Cargo Berth(GCB) in the
Outer Harbour at Vizag
Development of EQ-1 by replacement of Equity EQ-1 and Part of EQ-2 in
Inner Harbour to Handle Steam Coal
Developemnt of EQ-1A on South side of EQ-1 for Handling Thermal
Coal and Stem Coal
Kandla Port
Development of Dry Bulk Terminal off Tekra near Tuna
Development of 13th Berth other than liquid and container cargo berth)
Development of 15th multipurpose cargo berth
Development of 16th multipurpose cargo berth
Setting up of Captive Barge Jetty at Old Kandla (IFFCO)
Paradip Port
Construction of Deep Draft Iron Ore Berth
Construction of Deep Draft Coal Berth
Multi-purpose Berth at Paradip to Handle Clean Cargo including Containers
VOC Port, Tuticorin
Construction of Coal Berth at NBW for NLC – TNEB
Construction of North Cargo Berth-II
Ennore Port
Development of Container Terminal
Cochin port
LNG Re-gasification Terminal
Mumbai Port
Construction of Offshore Container Berths and Development of terminal on
BOT basis at Mumbai Harbour
New Mangalore Port
Setting up of Mechanised Iron OreHandling Facilities at Berth No- 14
Mormugao Port
Development of Coal Handling Teminal at Berth no- 7
JNPT
4th Container Terminal
Total
28-Dec-09
2-Mar-10
1-Mar-10
19-Mar-11
19-Mar-11
14.1
2.0
2.0
2.0
1.5
10.0
10.0
5.0
6.3
5.0
15.0
2.5
9.6
10.6
1.9
1.9
1.9
0.3
BOT
BOT
BOT
BOT
Captive
Feb-12
19-Sep-12
7-Dec-10
7-Dec-10
17-Feb-11
1-Jul-09
21-Aug-09
5-Jul-10
Jan-10
12-Aug-10
13-Aug-10
13-Mar-09
1-Apr-09
5.9 BOT
4.8 BOT
3.9 BOT
0.5 Captive
3.3 BOT
14.1 BOT
35.0 Captive
14.6 BOT
6.6
7.0
60.0
100.7
3.0 BOT
2.5 BOT
67.0 BOT
136.2
23-Sep-09
7-Aug-09
Aug-11
20 June 2012
8

Ray of Hope
| Infrastructure
Projects under Bidding stage
S.No Project Name
1
VOC Port, Tuticorin
Construction of Shallow draft berth for handling cement
Upgradation of mechanical handling equipments inberth no.1 to 6 and berth no.9
Constn. of shallow draught Berth(2 Nos) for handling construction materials
Conversion of berth no- 8 as Container Terminal
Development of NCB-III for handling thermal coal & rock phosphate V.O.C. Port Trust
Development of NCB-IV for handling thermal coal & Copper concentrate
Visakhapatnam Port
Installation of Mechanised handling facilities for fertilizers at EQ 7 in the Inner Harbour
Development of
WQ 7
for handling Import Dry bulk cargo at
Development of
WQ 8 for handling break bulk cargo and export bulk cargo
Installation of Mechanised Iron Ore handling facilities at
WQ-1)
in the northern arm of
Inner harbour of VPT for handling Dry bulk cargo
Chennai Port
Creation of Mega Container Terminal
Development of RO-RO cum multi-purpose berth & car parking at Bharthi Dock
Development of Barge jetty at Bharthi Dock
Kandla Port
Setting up of Single Point Mooring ( SPM ) and allied facilities off Veera in Gulf of Kutch
Upgradation of Barge Handling Facilities at Bunder Basin
Mechanisation of cargo berth No.7 & 8
Mormugao Port
Development of 4 MMTPA mechanised Coal Import Terminal at Berth No.11
Development of 7.2 MMTPA Iron ore export Bulk Handling Terminal west of breakwater
Kolkata Port
Construction of Outer Terminal 1 upstream of 3nd Oil Jetty with ancillary facilities on PPP basis
(linked with transloading facilities at Kanika/Sandheads)
Cochin Port
International Bunkering Terminal - Construction of Multi-purpose Liquid Terminal
JNPT
Development of standalone container handling facility with a quay length of 330m
North of NSICT Terminal
Total
Est. Cost
(INR B)
0.9
0.8
0.6
3.2
4.2
3.6
2.2
1.8
2.3
2.8
Capacity
(m tons)
2
8
2
7
7
7
5
5
2
9
2
3
36.9
1.0
0.3
6.2
0.9
0.8
4.3
7.2
2.9
48
1
1
12
3
7
4
7
5
4
5
6
7
8
2.1
6.0
91
4
10
158
20 June 2012
9

Motilal Oswal
Product Gallery
weekly
Motilal Oswal
Sector
Periodicals
power utilities monthly

Motilal Oswal Sector Gallery

Disclosures
This report is for personal information of the authorized recipient and does not construe to be any investment, legal or taxation advice to you. This research report does not constitute an offer, invitation or
inducement to invest in securities or other investments and Motilal Oswal Securities Limited (hereinafter referred as MOSt) is not soliciting any action based upon it. This report is not for public distribution
and has been furnished to you solely for your information and should not be reproduced or redistributed to any other person in any form.
Unauthorized disclosure, use, dissemination or copying (either whole or partial) of this information, is prohibited. The person accessing this information specifically agrees to exempt MOSt or any of its
affiliates or employees from, any and all responsibility/liability arising from such misuse and agrees not to hold MOSt or any of its affiliates or employees responsible for any such misuse and further agrees
to hold MOSt or any of its affiliates or employees free and harmless from all losses, costs, damages, expenses that may be suffered by the person accessing this information due to any errors and delays.
The information contained herein is based on publicly available data or other sources believed to be reliable. While we would endeavour to update the information herein on reasonable basis, MOSt and/or
its affiliates are under no obligation to update the information. Also there may be regulatory, compliance, or other reasons that may prevent MOSt and/or its affiliates from doing so. MOSt or any of its
affiliates or employees shall not be in any way responsible and liable for any loss or damage that may arise to any person from any inadvertent error in the information contained in this report . MOSt or any
of its affiliates or employees do not provide, at any time, any express or implied warranty of any kind, regarding any matter pertaining to this report, including without limitation the implied warranties of
merchantability, fitness for a particular purpose, and non-infringement. The recipients of this report should rely on their own investigations.
This report is intended for distribution to institutional investors. Recipients who are not institutional investors should seek advice of their independent financial advisor prior to taking any investment
decision based on this report or for any necessary explanation of its contents.
MOSt and/or its affiliates and/or employees may have interests/positions, financial or otherwise in the securities mentioned in this report. To enhance transparency, MOSt has incorporated a Disclosure of
Interest Statement in this document. This should, however, not be treated as endorsement of the views expressed in the report.
Disclosure of Interest Statement
1. Analyst ownership of the stock
2. Group/Directors ownership of the stock
3. Broking relationship with company covered
4. Investment Banking relationship with company covered
Larsen & Toubro
No
No
No
No
Adani Port
No
No
No
No
Analyst Certification
The views expressed in this research report accurately reflect the personal views of the analyst(s) about the subject securities or issues, and no part of the compensation of the research analyst(s) was, is,
or will be directly or indirectly related to the specific recommendations and views expressed by research analyst(s) in this report. The research analysts, strategists, or research associates principally
responsible for preparation of MOSt research receive compensation based upon various factors, including quality of research, investor client feedback, stock picking, competitive factors and firm revenues.
Regional Disclosures (outside India)
This report is not directed or intended for distribution to or use by any person or entity resident in a state, country or any jurisdiction, where such distribution, publication, availability or use would be contrary
to law, regulation or which would subject MOSt & its group companies to registration or licensing requirements within such jurisdictions.
For U.K.
This report is intended for distribution only to persons having professional experience in matters relating to investments as described in Article 19 of the Financial Services and Markets Act 2000 (Financial
Promotion) Order 2005 (referred to as "investment professionals"). This document must not be acted on or relied on by persons who are not investment professionals. Any investment or investment activity
to which this document relates is only available to investment professionals and will be engaged in only with such persons.
For U.S.
MOSt is not a registered broker-dealer in the United States (U.S.) and, therefore, is not subject to U.S. rules. In reliance on the exemption from registration provided by Rule 15a-6 of the U.S. Securities
Exchange Act of 1934, as amended (the "Exchange Act") and interpretations thereof by the U.S. Securities and Exchange Commission ("SEC") in order to conduct business with Institutional Investors
based in the U.S., Motilal Oswal has entered into a chaperoning agreement with a U.S. registered broker-dealer, Marco Polo Securities Inc. ("Marco Polo").
This report is intended for distribution only to "Major Institutional Investors" as defined by Rule 15a-6(b)(4) of the Exchange Act and interpretations thereof by SEC (henceforth referred to as "major
institutional investors"). This document must not be acted on or relied on by persons who are not major institutional investors. Any investment or investment activity to which this document relates is only
available to major institutional investors and will be engaged in only with major institutional investors.
The Research Analysts contributing to the report may not be registered /qualified as research analyst with FINRA. Such research analyst may not be associated persons of the U.S. registered broker-dealer,
Marco Polo and therefore, may not be subject to NASD rule 2711 and NYSE Rule 472 restrictions on communication with a subject company, public appearances and trading securities held by a research
analyst account.
Motilal Oswal Securities Ltd
Motilal Oswal Tower, Level 9, Sayani Road, Prabhadevi, Mumbai 400 025
Phone: +91 22 3982 5500 E-mail: reports@motilaloswal.com