Sector Update
| Infrastructure
Sector Update
| 8 April 2025
Infrastructure
Technology
Key Indicators
FY23 FY24
FY25
NHAI awarding picks up in 4Q, ends below target in FY25
Daily average
FASTag toll
1.5 1.8
2.0
collections
(INR b)
Tenders
awarded
6,003 2,500 4,080
by NHAI (km)
Road
construction 4,882 6,644 5,614
by NHAI (km)
NHAI’s project awarding in FY25 stood at 4,080km, below the 5,000km target, mainly
due to general elections in 1QFY25 and subdued activity until 3QFY25. Awarding
picked up in 4QFY25, with ~2,600km awarded during the quarter. The overall muted
awarding has impacted order inflows for several road construction companies. NHAI
exceeded its highway construction target of 5,150km and built 5,614km in FY25.
FASTag toll collections grew ~15% YoY in terms of volume and ~17% YoY in terms of
value in 4QFY25, supporting asset monetization plans.
In FY25, NHAI monetized assets worth INR287b, below the INR390b target, due to
MoRTH’s directive to pause ToT (toll-operate-transfer)-based monetization. However, it
raised a record INR177b through the fourth round of NHAI InVIT. For FY26, NHAI targets
INR300b in monetization, with 24 road assets (1,472km) identified for the process.
The Dedicated Freight Corridor Corporation of India (DFCCIL) has commissioned 2,741km
of the planned 2,843km for both the Eastern and Western Dedicated Freight Corridors
(DFCs). The completion deadline is extended to Dec’25 due to delays in land acquisition.
NHAI awarding remains subdued in FY25; construction activity exceeds
target
In FY25, NHAI awarded road projects totaling 4,080km, falling short of its initial
target of 5,000km. There were no project awards in 1QFY25 due to the general
elections, followed by subdued awarding activity in 2Q and 3Q. On a YoY basis,
project awards rose by 63%, largely due to the low base in FY24. Muted awarding
over the past two fiscals has significantly impacted order inflows for many road
construction companies. On the construction front, NHAI exceeded its highway
construction target of 5,150km by completing 5,614km in FY25. However, this still
marked a 15% YoY decline YoY.
FASTag toll collections showing consistent improvement
FASTag toll collection volume improved ~15% YoY in 4QFY25, while the collection
value increased ~17% YoY. During FY25, FAStag toll collections increased 13% YoY.
Higher toll collections play a crucial role in expediting the monetization process of
road assets by the Ministry. Additionally, toll collections benefit companies that aim to
monetize their existing toll assets.
Declining input prices to boost margins for contractors
Steel and aluminum prices have decreased ~25% and ~18%, respectively, from their
highs seen in Apr’22. Cement prices have decreased ~8% from their highs seen in
Oct’23. With higher construction activities and stability in commodity prices, road
contractors anticipate some improvement in profitability and margins in FY26.
Players with robust order books, strong balance sheets, and diversified
operations well placed
Although there has been a slowdown in project awarding in FY24 and FY25, the
tender pipeline is currently robust. Entities with significant order backlogs, strong
financial standings, and involvement across diverse sectors are well-positioned to
benefit.
Alok Deora - Research analyst
(Alok.Deora@MotilalOswal.com)
Saurabh Dugar - Research analyst
(Saurabh.Dugar@MotilalOswal.com)
Investors are advised to refer through important disclosures made at the last page of the Research Report.
Motilal Oswal research is available on www.motilaloswal.com/Institutional-Equities, Bloomberg, Thomson Reuters, Factset and S&P Capital.
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Awarding remains subdued in FY25
Exhibit 1:
NHAI’s awarding and construction trends (in km)
Tenders awarded by NHAI (in km)
Road construction by NHAI (in km)
Sources: NHAI, MOFSL
Project awarding by NHAI totaled 4,080km in FY25 vs. the target of 5,000km at
the start of FY25. Order awarding by NHAI was NIL in 1QFY25 due to the general
elections, followed by subdued awarding in 2Q and 3Q of FY25. On a YoY basis,
awarding increased by 63% YoY primarily due to a lower base of FY24. Muted
awarding by NHAI in the last two fiscals has severely affected order inflows for
several road construction companies.
On the construction side, NHAI exceeded its highway construction target of
5,150km and built 5,614km in FY25. However, compared to FY24, construction
activity was lower by 15%. NHAI also reached an all-time high capex of INR2.5t in
FY25, exceeding the target of INR2.4t.
8 April 2025
2
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Exhibit 2:
List of civil projects awarded during Apr’24-Feb’25
Sr.
Project Name
No.
Construction of 6 lane elevated corridor including its
approaches from Km. 629+880 to Km. 634+470 (Design
Chainage) of NH-16 in Ranasthalam Town portion in the state
of Andhra Pradesh on EPC Mode under NH(O).
Access Controlled Highway of 4 Lane with Paved Shoulders
from TN/AP Border (Design Chainage Km 61+51) to Puttur
(Design Chainage Km 81+540) of NH-716 & 6 Lane with Paved
Shoulders from Mallavaram to Renigunta
Guwahati Ring Road in the State of Assam
NH(New)
Total
Length
(Kms)
4.59
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
27-12-2024
1.38
PIU
Mode
Concessionaire
State
1
16
Visakhapatnam
EPC
Srinivasa Edifice Private
Limited.
Andhra Pradesh
2
716, 71
NH-27,NH-
37,NH-31
37.43
11-03-2024
8.62
Chennai-II
HAM
BOT
Toll
EPC
HG Infra Engineering
Limited
Dineshchandra R. Agrawal
Infracon Pvt. Ltd.
Ashoka Buildcon Limited
Andhra Pradesh
3
4
121.43
29.827
06-02-2025
07-02-2024
49.55
5.20
Guwahati
Aurangabad_BR
Assam
Bihar
5
6
7
8
9
10
6L of Aurangabad to Bihar-Jharkhand border (Chordaha)
19
section from km. 180.000 to km. 209.827 of NH-2 (PKG-01)
Permanent rectification of 4 Nos. of blackspots on NH-27 (old
NH-28) of Kotwa – Mehsi - Muzaffarpur Section from Km
440.00 to Km520.00 (Total length 80.00 Km); 4 nos. of
blackspot on NH-27 of Muzaffarpur – Darbhanga – Purnia
27,27,122
section (Km.0.00 to Km 148.550 and Km 159.357 to Km
287.860) (total length 277.053 Km.) & 1 No of at -grade
junction removal near Satanpur junction in
Construction of Flyovers at (i) Major Junction between NH-77
& SH-49 (Y- Junction) at Mahua Chowk & (ii) Intersection
NH-22,NH-
between NH-77 & MDR (Lalganj to Muzaffarpur) (Y-Junction) at
22
Fakuli in four-laning of Hazipur & Muzaffarpur Section of Nh -
22
Construction of 2 flyovers of 4- lanes at Chhatauni Chowk and
Awadesh Chowk on the Piprakothi- Motihari- Raxaul section of
NH-28, Re-construction of 3 no. of gantry girder gates with the
statue of Mahatma Gandhi on NH-28 and NH-28A &
527D,27
Construction of Service Road and Drain near Piprakothi on
NH27(Old-NH28) Kotwa – Mehsi- Muzaffarpur Section from km
440.00 to km 520.00(Under TOT)
Bakhtiyarpur-Rajauli Pkg-I from km. 47.723 to km. 54.405
20
Widening with additional 3L abetting Chhapra Bypass Section
NH-31
of NH-19 from Km. 143.200 to Km. 159.255 (Pkg-1)
Construction of Major Bridge over Baghmati and Lakhandei
River along with Approaches from Design km.16.500 to
527C
km.21.500
10.259
09-03-2024
2.36
Darbhanga
EPC
Dhariwal Buildtech Limited
Bihar
2.51
14-03-2024
0.70
Patna
EPC
JSP Project Pvt Ltd.
Bihar
3.335
26-03-2024
0.50
Motihari
EPC
Amber Infraproject Pvt.
Ltd.
Bihar
6.682
16.05
5
15-03-2024
06-03-2024
11-03-2024
1.37
3.03
2.68
Gaya
Chhapra
Darbhanga
EPC
EPC
EPC
KCC Infra Private Limited
R K Jain Projects Private
Limited
ASC Infratech Pvt. Ltd.
Bihar
Bihar
Bihar
8 April 2025
3
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
11
4L of Pathalgaon-Kunkuri-CG/JH Border section of NH-43 from
Km. 00.000 to Km.104.250
Construction of 4L Flyover from MES College Junction to
Bogmalo Junction on NH-566 from Km. 7.106 to Km. 10.460
and 4L VUP at Queeny Nagar Junction from Km. 3.330 to Km.
4.550
Balance work of Six Laning of Shamlaji- Motachiloda from Km.
401.200 to Km.494.410 section (Design Chainage Km.447.385
to Km 540.595, Length- 93.210 Km) of old NH-8 (NH-48) in the
state of Gujarat on single Percentage
Construction of Six Lane Flyover at the Junction of Kandari
Chokdi (Ch. 149+440) and Luvara Patiya (Ch. 186+640) for
Rectification of Blackspots on Vadodara - Surat Section of NH-8
4L of Dhrol bypass section of NH-151A (Approx. length 5.7 Km)
& widening upto 4 laning of missing link of Amran section of
NH-151A (Approx. length 6.55 Km) from existing Ch. 42+000 to
48+500 of ongoing Dhrol-Bhadra-
Construction of 04 nos. of MoRTH identified Blackspot on
Jetpur-Somnath section of NH-151
4L PS from Ch. 94.030 in Jabugam Village to Ch. 132.320 in
Dhamasiya Village of NH-56 (Pkg-III)
4L PS from Ch. 179.780 in Bitada/Movi Village to Ch. 208.900 in
Nasarpore Village of NH-56 (Pkg-V)
Construction of Vehicular Underpass (VUP) at Daman Ganga
(Ch.368.850 km) Including Service Road, Culverts and Minor
Bridge between Daman Ganga River and Mohan Gam Railway
for Rectification of Blackspot ID GJ-(02)- 066 on Surat-Vapi
Section of NH-8 (New NH-48) in the state of Gujarat on EPC
Mode
Long Term Rectification Works - Construction of Three Lane
River Bridge at Bhukhi Khadi (Ch. 176+420) and Amravati Khadi
(Ch. 202+845), Additionally Construction of Service Road of Ch.
114+470 to 116+180 (Vadodara-Bharuch) and Ch. 186+885 to
190+675 (Bharuch-Surat) for Blackspot on Vadodara-Surat
Section NH-8 (New NH-48) in the state of Gujarat on EPC
4 Lane LVUP at Sector-26 Panchkula Junction at Km. 170+335
of Yamunanagar - Panchkula Section of Old NH-73 (New NH-
07) from Km. 169+700 to Km. 170+950
Total
Length
(Kms)
104.25
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
10-01-2025
19.53
NH(New)
43
PIU
Korba
Mode
HAM
Concessionaire
Krishna Constellation Pvt.
Ltd.
M. Venkata Rao Infra
Projects Pvt. Ltd.
State
Chhattisgarh
12
566
4.574
07-03-2024
2.38
Goa
EPC
Goa
13
48
5.54
28-06-2024
4.15
Ahmedabad
Item
Rate
Apex Tarmac Pvt. Ltd.
Gujarat
14
48
2.48
09-02-2024
0.60
Ekta Nagar
EPC
Shiwalay Infra Projects Pvt
Ltd
Gujarat
15
151A
12.25
13-03-2024
3.16
Rajkot
EPC
MKC Infrastructure Ltd.
SRM Contractors Ltd. in JV
with Sarvangik Infra Private
Limited
Dineshchandra R. Agrawal
Infracon Pvt. Ltd.
Wagad Infraprojects Pvt
Ltd
Gujarat
16
17
18
151
56
56
3.5
38.29
29.12
19-12-2024
08-03-2024
11-03-2024
0.90
8.24
5.31
Rajkot
Ekta Nagar
Ekta Nagar
EPC
HAM
HAM
Gujarat
Gujarat
Gujarat
19
48
1.85
05-12-2024
0.37
Surat
EPC
Meher Foundations&. Civil
Engineers Pvt. Ltd.
Gujarat
20
48
7.5
27-11-2024
0.59
Surat
EPC
New India Contractors &
Developers Pvt Ltd
Gujarat
21
07
1.25
02-07-2024
0.14
Chandigarh
EPC
Rajinder Infrastructure
Private Limited
Haryana
8 April 2025
4
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
4 laning of Aligarh-Palwal Section from Km. 46.390 (Design
Chainage) to Km. 69.110 (Terminating at junction EPE)
(Package-II from Kurana- Eastern Peripheral Expressway) of
NH-
4L PS from Kalar Bala Village to Nauni Chowk of NH 205 from
Km 41.000 to Km 58.450
Construction of Slope Protection Work at Various Locations on
the Hillside between Km 67+000 to Km 106+139 of the
Parwanoo-Solan section of NH 22 (now NH 5) on EPC mode in
the State of Himachal Pradesh (HP)
Upgradation and Strengthening of Chenani to Nashri Section
via Patnitop of NH244 from Km 0.000 to Km 39.100
4 Lane of CG/JH Border-Gumla from km 0.000 to km 32.370 of
NH-43 in the State of Jhrkhand
4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma
(Jamshedpur) Section of NH- 33 (New NH-18) (from km
241+940 to km 251+961) (Length 10.021 km)
4L from Km 55.00 (Kuru) to Km 95.400 (Udaipura) on NH-75
(Sec-I)
4 Lane with PS from Des. Ch 136.100 to Des. Ch. 182.300 of
Belgaum-Hungund-Raichur Section of NH-748A (Package-4)
Total
Length
(Kms)
22.72
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
01-08-2024
6.77
NH(New)
PIU
Mode
Concessionaire
State
22
334D
Aligarh
HAM
Nirmal Build Infra Pvt. Ltd.
Haryana, Uttar
Pradesh
Himachal Pradesh
23
205
17.45
08-03-2024
6.40
Hamirpur
HAM
Gawar Construction Ltd
24
NH-O5
2.96
11-03-2024
1.00
Shimla
EPC
SRM Contractors Limited Himachal Pradesh
SRM Contractors Limited -
DMR Builders Private
Limited (JV)
Shivalaya Construction Co.
Pvt. Ltd.
H.G. Infra Engineering
Limited
Barbrik Project Limited
Bekem Infra projects Pvt.
Ltd- M/s DHD Infracon
Private Limited
(consortium )
Bekem Infra projects Pvt.
Ltd- M/s DHD Infracon
Private Limited
(consortium )
MKC Infrastructure Ltd.
DHD Infracon Private
Limited M/S Bekem Infra
projects Pvt. Ltd (
Consortium )
SRC Infra Developers
Private Limited
25
26
27
28
244
NH-43
NH-33
75
39.1
32.37
10.021
38.6
11-03-2024
07-10-2024
09-03-2024
07-03-2024
2.36
7.81
6.10
8.10
Udhampur
Gumla
Ranchi
Daltonganj
EPC
HAM
EPC
HAM
Jammu and
Kashmir
Jharkhand
Jharkhand
Jharkhand
29
748A
46.2
09-03-2024
7.89
Bagalkot
HAM
Karnataka
30
4 Lane with PS from Des. Ch 89.900 to Des. Ch. 136.100 of
Belgaum-Hungund-Raichur Section of NH-748A (Package-3)
4 Lane with PS from Des. Ch 43.800 to Des. Ch. 89.900 of
Belgaum-Hungund-Raichur Section of NH-748A (Package-2)
4 Lane with PS from Des. Ch 0.000 to Des. Ch. 43.800 of
Belgaum-Hungund-Raichur Section of NH-748A (Package-1)
4LPS Access Controlled Highway of Bellary Bypass (Balance
work) from Ch. 254+750 to Ch. 266+837 and construction of
4LPS from Ch. 277.690 to Ch. 278.690 at D. Hirehal Village
(Balance work) of NH 150A of Bellary –
748A
46.2
09-03-2024
8.49
Bagalkot
HAM
Karnataka
31
748A
46.1
11-03-2024
8.29
Bagalkot
HAM
Karnataka
32
748A
43.8
11-03-2024
7.90
Bagalkot
HAM
Karnataka
33
150A
13.087
13-03-2024
2.81
Hospet
EPC
Karnataka
8 April 2025
5
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
Total
Length
(Kms)
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
NH(New)
PIU
Mode
Concessionaire
State
34
35
36
37
38
39
40
41
Construction of VUP (Talkere Hand Post-KA- (02)-057), LVUP
(Agrahara Junction- KA (02) -273) and VUP (Tippasandra Hand
Post- KA (02) -015) of MORT&H Identified Black Spots on
75
Devihalli-Hassan section of NH-75 to be executed on
Engineering Procurement and
Construction of Long Term Remedial Measures for Blackspot
Locations at (1) 4-Lane VOP at Yelachagere Bore gate Km
177+348, (2) 4-Lane VUP at Kalale Gate Km 184+100, (3) 2-
Lane LVUP at Hoshalli Gate Km 185+510, (4) 2-lane VUP at
Kadakola junction 198+210, (5) 4-Lane VUP’s at APMC Gate Km 7,66,275
206+360 & 206+535, (6) 2-Lane VUP at Sachidanada Ashrama
Km 208+254 and (7) 4-Lane VUP at Kempaiahnahundi Km.
232+493 along Kerala Border to Kollegal Section of NH-766 and
(8) 4-Lane VUP at Bannikuppe Km 181.637 along
Construction of Vehicular underpass at Kudal Sangam cross at
Km.305+446 (Black spot ID: KA-(02)-367) & Vehicular
underpass at Belgal cross at Km.307+151 (Black spot ID:KA-
50
(02)-249) on the 4 lane Bijapur-Hungund section of
NH-50 from Km.225.800 to Km.323.012 in the state of
Karnataka to be executed on EPC Mode
Construction of Vehicular Underpass (VUP) at Km. 487.324
(Black Spot No. TG-02-002 (Nandikandi outskirts)) and
Construction of Flyover (Black Spot No.KA-02-323 (Chidri
65
Bypass) for Four Laning of MH-KNT Border- Sangareddy from
KM.348.800 to KM.493.000 in the State of Karnataka and
Telangana of NH-09
Balance work of widening of 4 nos existing 2 Lane major Bridge
of Six-laning of Kozhikode Bypass (Calicut Bypass) (i.e.
Vengalam Jn. to Ramanattukara Jn.) section of NH-66 from
66
Design Chainage km 230+400 to Design Chainage km 258.800
(total length 28.400 km)
Construction of Standalone Flyover at Rasalpur Junction on
Indore-Dewas section of NH-52 under road safety
NH-52
improvement in the state of Madhya Pradesh on EPC mode
2L PS of Roshni to Ashapur Section of NH-347B from Design KM
347b
Ch. 89.900 to 114.000 KM (Package – III of Betul – Khandwa)
4L from km 0.000 to 42.040 Bhopal (Ratnaigiri Tiraha) to
146
Vidisha (Morikodi)
3.123
15-03-2024
0.66
Hassan
EPC
Abdul Kalam Azad
Karnataka
8.1
12-03-2024
1.27
Mysuru
EPC
Krishi Infratech
Karnataka
2.3
14-12-2024
0.44
Bagalkot
EPC
H P Madhukar & Co
Karnataka
1.94
15-03-2024
0.56
Gulbarga
EPC
KOTARKI Constructions Pvt
Ltd
Karnataka,
Telangana
1.895
30-05-2024
1.06
Kozhikode
EPC
KMC Construction Ltd.
Kerala
1.133
24.1
42.04
27-06-2024
14-03-2024
08-01-2025
0.31
1.04
7.43
Indore
Khandwa
Bhopal
EPC
EPC
HAM
Punia Construction Co.
SCONS Infrastructure
Private Limited
VRC Constructions (India)
Pvt. Ltd.
Madhya Pradesh
Madhya Pradesh
Madhya Pradesh
8 April 2025
6
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
42
43
44
Total
Length
(Kms)
28.886
55.125
43.924
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
09-01-2025
07-01-2025
03-01-2025
3.50
6.14
5.87
NH(New)
PIU
Mode
Concessionaire
Radhakrishan Infra
Developers Pvt. Ltd
Velji Ratna Sorathia Infra
Pvt. Ltd.
MKC Infrastructure Ltd.
State
45
46
47
48
49
50
51
52
53
4L Vidisha Gyaraspur section of NH-146 from Design Chainage
km 59+475 (existing chainage km 81+240 ) to Design Chainage
146
km 88+361 (existing chainage km 110.315)
4L of near Satai Ghat to Chowka section of NH- 34 from D. Ch.
34
89.875 to D. Ch. 145.000 (Package-3)
4L of Chowka to Kaimaha near MP/UP Border section NH-34
from D. Ch. 145.000 to D. Ch. 197.266 excluding existing
34
Chhatarpur bypass from D. Ch. 160.307 to D. Ch. 168.630
4-lanning of Gyaraspur to Rahatgarh section of NH-146 from
Design Ch. 88+361 to Ch 124+470 in the state of MP on HAM
NH-146
mode
Outer Ring Road of Jabalpur Town from Amjhar Road including
na
Airport Connectivity to barela (Pkg-V)
Balance Work for Construction of Two lane with paved
shoulder from Km 80+800 to Km 85+250 (Satna-Maihar
section) of NH 135BG (design length 4.450 km) under
135BG
Bharatmala Pariyojana in the State of Madhya Pradesh on EPC
Mode
Balance works of 4 lane divided carriageway of Missing Link
section of NH-39 (Rewa Bypass) from junction with NH 30 near
Bela to Junction with MPRDC ring road near Silpara on SH 9
39
(design length 13.100 km) on EPC Mode under Bharatmala
Pariyojana in the State of Madhya
Construction of Light Vehicular Underpass (LVUP) at
Gandhinagar Junction at Km 320.100 and Vehicular Underpass
(VUP) at Doraha Junction at Km 341.070 Lalghati (315.725) to
46
Biaora (421.325) section of NH-12 (New NH-46) in the state of
Madhya Pradesh on EPC Mode.
Construction of 6 lane Indore western bypass from km 0+000
to Km 34+000 (Pkg -l ) in the State of Madhya Pradesh on
0
Hybrid Annuity Mode under NH(O)
Construction of 6 lane Indore western bypass from km 34+000
to Km 64+000 (Pkg-II) in the state of Madhya Pradesh on
0
Hybrid Annuity Mode under NH(O)
4L of Budhni to Shahganj Bypass End (Package- III) of NH-146B
146B
from Km. 73.750 to Km. 102.000
Construction work of 4-laning of Shahganj bypass end to Badi
(Package-IV) of NH-146B from design km 102.000 to design km
146B
142.357 (Design length 40.357 km)
Vidisha
Chhattarpur
Chhattarpur
HAM
HAM
HAM
Madhya Pradesh
Madhya Pradesh
Madhya Pradesh
36.109
18.55
09-01-2025
06-01-2025
5.37
4.02
Vidisha
Jabalpur
HAM
HAM
MKC Infrastructure Ltd.
Velji Ratna Sorathia Infra
Pvt. Ltd.
PKT Construction Private
Limited
Madhya Pradesh
Madhya Pradesh
4.45
30-12-2024
0.41
Katni
EPC
Madhya Pradesh
13.1
16-02-2024
2.26
Katni
EPC
Udit - PRL(JV)
Madhya Pradesh
2.452
23-09-2024
0.26
Bhopal
EPC
Godec Construction Pvt.
Ltd. Shivpuri
Madhya Pradesh
34
12-03-2024
9.96
Indore
HAM
MKC Infrastructure Ltd.
Madhya Pradesh
30
28.25
40.357
12-03-2024
16-03-2024
15-03-2024
8.84
5.09
5.19
Indore
Bhopal
Bhopal
HAM
HAM
HAM
MKC Infrastructure Ltd.
Mundan Construction
Company
Mundan Construction
Company
Madhya Pradesh
Madhya Pradesh
Madhya Pradesh
8 April 2025
7
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
54
Six laning with both sides Service Road of Ayodhya Bypass from
Design Km 0+000 near Ashram Tiraha on NH-46 to Km 16+439
end at Ratnagiri Tiraha on Nh-146
Design and Construction of VUP along with its allied works for
rectification of MoRTH identified blackspot [Blackspot ID: MH
(05)-20)] at Ibadpada/ Sutrakar Phata (Ch.392.500) on Surat-
Dahisar section of NH-48 in the state of
Construction of Major Bridges (Service Road Bridges) at Krishna
River including approaches for Rectification of Black Spot (MH-
04-218) on both sides at Km 756+395 (Krishna River Bridge)
and Construction of Flyover including a LVUP and Approaches
for Rectification of Black Spot (MH-04-216) on both sides at Km
770+550 (Vele Village) of Pune-Satara Section of NH-48 in the
State of Maharashtra on EPC Mode
Design and Construction of New Service Road from Ch. Km.
835.780 to Km. 836.600 (Linear length km 1.605) including
Minor Bridges And New Major Bridges on Both sides Service
Road on Mutha River Ch.837+063 along with its approaches for
NH-4 (Pune-Satara Section Km.725.000 to Km. 865.000) in the
State of
6L of Gonde (Km. 439.038) to Pimpri Sado (Km. 459.905)
section of NH-848 (Old NH-3)
6L Saundad ROB on Raipur-Nagpur (from 441.970 km to
443.560 km)
Design & Construction of Vehicular Underpass (VUP) at
Khadakjamb at Ch. 373+430 & Light Vehicular Underpass
(LVUP) at Ch. 373+650 in the State of Maharashtra on EPC
Mode
Construction of Service Road at Laling, Mungase, Vadalibhoi &
Raigad Nagar and Road Safety Works in Rahud Ghat in the
State of Maharashtra on EPC Mode
Strengthening of 6-lane Pimpalgaon-Nashik- Gonde (Km. 380 -
Km. 440) section of NH-3 in Maharashtra using Thin White
Topping (TWT) and BC Overlay on Service Road & Viaduct/Deck
of Structures on EPC mode
Design and Construction of Vehicular Underpass as Long-term
rectification work at MoRTH Blackspot i.e. Dongarbaba Temple
(MH-04-192) at Ch. 425.510 on Pimpalgaon-Nashik-Gonde
Section of NH-3 in the State of Maharashtra on
Total
Length
(Kms)
16.439
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
02-12-2024
8.37
NH(New)
Missing
Link
PIU
Mode
Concessionaire
Ravi Infrabuild Projects
Limited
State
Bhopal
HAM
Madhya Pradesh
55
NH 48
1
26-06-2024
0.34
Thane
EPC
Shiv Sai Construction
Maharashtra
56
48
2.05
06-03-2024
0.43
Pune
EPC
MD-Infra India Pvt. Ltd.
Maharashtra
57
48
1.6
30-08-2024
0.53
Pune
EPC
Nikhil Construction Group
Private Limited
Maharashtra
58
59
03
53
19.712
1.6
12-03-2024
12-09-2024
5.74
0.33
Nashik
Nagpur (PD-1)
HAM
EPC
CDS Infra Projects Limited
Pilcon Engineering
Maharashtra
Maharashtra
60
3
1.2
24-09-2024
0.33
Nashik
EPC
Trimurthy Construction
Maharashtra
61
3
8.66
26-09-2024
0.45
Nashik
EPC
Vijay Kumar Contractor
Maharashtra
62
03
60
02-03-2024
1.75
Nashik
EPC
Raj Infrastructure
Development (I) Pvt. Ltd.
Maharashtra
63
3
1.22
11-03-2024
0.39
Nashik
EPC
FORCON INFRA PVT. LTD.
Maharashtra
8 April 2025
8
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
Total
Length
(Kms)
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
NH(New)
PIU
Mode
Concessionaire
State
64
65
66
67
68
69
70
71
72
73
Design and Construction of Major Bridge along with its allied
works for rectification of blackspots at Bale Bridge (Ch.
245+700) and at Old Pune Naka Bridge (Ch. 246+600) on Pune -
65
Solapur (Km. 150.050 to Km. 251.325) section of NH 65 in the
State of Maharashtra
Four laning from Dive Ghat (Km. 220.900) to Hadapsar (Km.
965
234.150) of Mohol – Alandi section (Pkg – VI) of NH-965
Up-gradation to Four Lane with Paved Shoulder configuration
of the highway starting from existing km 88.400 (Savali Vihir) to
km 163.400 (start of Ahmednagar bypass) (Design Length –
160
75.000 km) section of NH-160 in the State of Maharashtra
under Bharatmala Pariyojana on
Development of Kalamboli Junction (3 level) comprises of (a)
connecting links from Sion Panvel Highway (SH) to NH-548
(which is connected to NMIA) (b) Connecting link to & from
548
Mumbai Pune Expressway to NH-548 (which is connected to
NMIA) (c) Connecting NH-48 to (i) Sion Panvel Highway (SH) &
(ii) Mumbai Pune Expressway through grade
Construction of 05 nos. of VUP i.e. at Km. 434+150, Km.
452+150, Km. 456+000, Km.462+670, Km. 466+270 and 01 no.
Flyover at Km. 442+610 with Approach Roads, in Puintola to
16
Icchapuram Section of NH-16 in the State of Odisha & Andhra
Pradeshon Engineering Procurement and Construction
Construction of 6-lane flyover at Ainthapali junction and a 2-
lane ROB (LHS) on NH-53 (Earlier NH-6) in Sambalpur, on EPC
53
mode in
6L Flyover including RE Wall approaches with Flexible
Pavement in the Elephant Corridor of Angul – Sambalpur
42
Section of NH-42 (New NH-55) Km.202.533
Construction of 6 laning flyover at Km. 178.250 (Baba Bal Nath
Samadhi Sthal) on Gurgaon Kotputli Jaipur section of NH 48 in
NH-48
the state of Rajasthan on EPC Mode
Construction of Balance Works of Two Number of Interchanges
at Jaipur Ring Road (NH-148C) from Tonk Road (NH-52) to
NH-148C
Ajmer Road Section (NH-48) in the State of Rajasthan on
Engineering, Procurement & Construction (EPC)
Construction of Four lane Elevated Structure at Raniwada
68
Circle in Sanchore City on NH-68
1.04
26-07-2024
0.35
Solapur
EPC
Nikhil Construction Group
Private Limited
R&C Infraengineers Pvt.
Limited
Bharat constructions
(India) pvt. Ltd
Maharashtra
13.25
09-03-2024
3.27
Pune
HAM
Maharashtra
75
04-02-2025
5.15
Ahmednagar
EPC
Maharashtra
15.53
10-10-2024
7.70
Panvel
EPC
Maharashtra State
Infrastructure
Development Corporation
Ltd(MSIDC)
Maharashtra
6
30-12-2024
1.15
Berhampur
EPC
NIRAJ CEMENT STRUCTURE
LTD
Odisha
3.44
15-03-2024
1.74
Sambalpur
EPC
ASC Infratech Pvt. Ltd.
Agrawal Infrabuild Private
Limited
Welkin India Incorporate
Sheeraj Project Pvt Ltd in
JV with KCC Buildcon Pvt.
Ltd.
Vidya InfraBuilt Pvt. Ltd.
Odisha
2
29-02-2024
0.90
Sambalpur
EPC
Odisha
1.13
13-03-2024
1.92
Jaipur
EPC
Rajasthan
6.872
04-03-2024
1.07
Jaipur
EPC
Rajasthan
6.2
02-03-2024
1.87
Jaisalmer
EPC
Rajasthan
8 April 2025
9
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
74
Construction of Trumpet Interchange Connecting Bangalore –
Chennai Expressway (km.261+705 to km. 262+800) with
Maduravoyal to Walajapet Section of NH 48
Balance Works for six laning of Sriperumbudur to karaipettai
section of NH-4 (New NH-48) from 37+000 (Existing Km
37+000) to Km 71+015 (Existing Km 71+000) in Tamilnadu on
EPC mode underNHDP Phase-V
Improving the Alignment of Thoppur Ghat Section from Km
158.500 to Km 165.100 in Dharmapuri - Salem Section of NH-
44
Walajahpet/Ranipet to TN/AP Border Section of from
Km.106.800 to Km.133.36 NH-4
Access Controlled Highway of 4 Lane with Paved Shoulders
from Tiruvallur (Design Chainage Km 17+56) to TN/AP Broder
(Design Chainage Km 61+51) of NH-716 (Chennai-
Construction of 6-lane Vehicular Underpass (VUP) (1X30X5.5)
@ Km.60+796 (i.e., Balanagar) along with Slip & Service Roads
under MoRTH identified Black Spot ID: TG-(02)-058 for the
period 2015-18 on Hyderabad-Bangalore section of NH-44 in
the state of
Construction of 6-lane Underpasses (4 No’s) and Allied works
on Existing 4 Lane Hyderabad- Bangalore Section of NH-44
from Km 89+000 to Km 124+000 in the State of Telangana on
EPC Mode, as part of Long-term Rectification of MoRTH
Identified Black Spots (TG-02-75, TG-02-97, TG-02-174 & TG-
02-59).
“Construction of 6-Lane Underpasses (2 No’s) and allied works
on Existing 4 Lane Hyderabad to Bangalore Section of NH-44
Kanimetta (from km 125.890 to km 127.250) & Thomalapally
(from km 149.110 to km 150.760) in the State of Telangana on
EPC Mode, as part of Longterm Rectification of MoRTH
Identified Black Spot
Construction of 6-Lane Underpasses (2 No’s) and allied works
on Existing 4 Lane Hyderabad to Yadgiri Section of NH-163 at
Ankushapur (from Km.26+145 to Km.27+295) & Kondamadugu
Jn. (From Km.30+505 to 32+125) in the State of Telangana on
EPC Mode, as part of Long-term Rectification of MoRTH
Identified
Total
Length
(Kms)
1.1
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
10-01-2024
1.12
NH(New)
NE-7 &
NH-48
PIU
Mode
Concessionaire
Ramalingam Construction
Company Pvt. Ltd
P&C projects private
Limited
State
Kanchipuram
EPC
Tamil Nadu
75
NH 48
16.82
07-11-2024
3.42
Kanchipuram
EPC
Tamil Nadu
76
77
78
44
40
716
6.6
28.08
43.95
09-03-2024
24-01-2025
09-03-2024
5.48
7.00
9.16
Salem
Krishnagiri
Chennai-II
HAM
HAM
HAM
Dilip Buildcon Ltd.
KCC Buildcon Pvt. Ltd.
Oriental Structural
Engineers Pvt. Ltd.
Tamil Nadu
Tamil Nadu
Tamil Nadu
79
44
1.26
08-03-2024
0.22
Hyderabad
EPC
BB Verma
Telangana
80
44
6.21
07-03-2024
1.02
Mahabubnagar
EPC
MSR Constructions
Telangana
81
44
3.01
26-09-2024
0.43
Mahabubnagar
EPC
Sree Rama Constructions
Telangana
82
163
2.77
28-01-2025
0.33
Warangal
EPC
Srinivasa Edifice Private
Limited.
Telangana
8 April 2025
10
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
Construction of Ring Road around kanpur from Ch.51.200 to
Ch. 68.650 (Badarka to Harbanch- Uchti Pkg-III)
Total
Length
(Kms)
18.9
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
22-08-2024
6.13
NH(New)
PIU
Mode
Concessionaire
HILLWAYS CONSTRUCTION
COMPANY PVT. LTD.-M/s
gour tar Road coat private
limited (JV)
Ajay Prakash Associates-
S.S. Builders (JV)
State
83
TBD
Kanpur
EPC
Uttar Pradesh
84
85
86
87
88
89
90
91
92
93
Construction of Ring Road Kanpur from Ch. 32.090 to
TBD
Ch.51.200 (Transganaga to Sathara) (Package-II B)
Construction of VUP Flyover at Medical Tiraha to
Konchhabhawar, Jhansi (Km. 105.700 to Km. 106.800) on NH-
25 (New NH-27) and Inter- change at Km. 97.100 on NH-25
27
(new NH-27) for Shivpuri-Kanpur Road (Jhansi Bypass) section
in the State of Uttar Pradesh on EPC.
4/6L of Northern Ayodhya Bypass starting Km. 112.540 and
ending Km. 139.928 north of existing NH-27 (part-1) and part-2 bypass
south of NH- 27 from km 0.000 to km 5.000.
4/6L Southern Ayodhya Bypass from Km 5.000 to Km 37.172
(starting near Km. 112.540 and ending at Km. 153.281 of NH-
bypass
27)
Six Lane Flyover with Service Road at Km 260+350 (On Bareilly
Bypass) on NH-30 (Old NH-24) of Moradabad-Bareilly Section in
30
the State of Uttar Pradesh on EPC Mode
4 lanning of Aligarh Palwal section from km 0.00 to km 46.39
package -1 from (khereshwar junction-kurana) of NH33D ,
334 D
including khair & jattari bypass in the state of UP on HAM
mode
Construction of 2L PS Pratapgarh Bypass from Km 150.900 to
31
Km 203.300 of NH-31
Construction of 4 – lane Kotdwar Bypass of NH – 119 in the
119
State of Uttar Pradesh and Uttarakhand on EPC Mode
Construction of 4 Lane Access Controlled Bypass for Dehradun
on NH307 from Design Chainage km 0+050 (Jhajra on NH-07)
7
to Design Chainage km 12+220 (Asharori) on EPC Mode in the
State of Uttarakhand under NH(O)
•Construction of 4 Lane VUP at 35.370 at Fatapukur along with
RE wall & Service Road in the Ghoshpukur-Dhupguri Section of
31D
NH-31D(New NH-27)
Dhupguri-End of Falakata Bypass (Pkg IIB)
31D
19.11
20-11-2024
3.21
Kanpur
EPC
Uttar Pradesh
2
14-08-2024
0.99
Jhansi
EPC
Gawar Construction Ltd
Uttar Pradesh
35.4
23-09-2024
11.99
Raebareli
HAM
Ceigall India Ltd.
Uttar Pradesh
32.172
23-09-2024
12.99
Raebareli
HAM
Ceigall India Ltd.
PRL Projects and
Infrastructure Limited
Uttar Pradesh
1.415
07-03-2024
0.30
Moradabad
EPC
Uttar Pradesh
46.39
13-03-2024
8.22
Aligarh
HAM
CDS Infra Projects Limited
Uttar Pradesh
50.8
5.95
13-02-2025
11-03-2024
5.65
2.58
Raebareli
Najibabad
HAM
EPC
SKS Infra Projects Pvt. Ltd.
ASC Infratech Pvt. Ltd.
BRN Infrastructure Private
Limited in JV with Ganesh
Builders
Mukherjee Associates Infra
(P) Ltd.
S&P Infrastructure
Developers Pvt. Ltd. -
Skylark Infra Engineering
Pvt. Ltd. (JV)
Uttar Pradesh
Uttarakhand
12.17
21-02-2024
2.70
VasantViharDehr adun
EPC
Uttarakhand
2
25-01-2024
0.15
Jalpaiguri
EPC
West Bengal
94
29
14-11-2024
7.17
Jalpaiguri
EPC
West Bengal
8 April 2025
11
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Sr.
Project Name
No.
95
96
97
98
99
100
101
Balance Works of 4L of NH-31D from Km. 113.200 to Km.
154.854 (Package-II A) Ghoshpukur-Salsalabari Section
4L Chandrakona-Ghatal Road Crossing to near Indus - Akui
Road section from Km 41.000 to Km 89.814 of NH 116A (Pkg-II)
4L Bowaichandi to Guskara–Katwa Road section from Km
89.814 to Km 133.000 of NH 116A (Pkg-III)
4L Mayurakshi Bridge Approach to Moregram section from Km
180.000 to Km 230.957 of NH 116A (Pkg-V)
4L Kharagpur to near Chandrakona-Ghatal Road Crossing
section from Km 0.000 to Km 41.000 of NH 116A (Pkg-I)
4L PS Kharagpur-Bardhaman-Moregram section from Km.
133.00 to Km. 180.00 for Package-IV
4 laning of Barasat - Barajaguli Section of NH-12 from Km.
31.000 to Km. 48.679 in the district of North 24 - Parganas
Development to 4-laning of the de-scoped stretches from Km
115.342 to Km 191.700 of NH-34 in Nadia District (3.962) &
Murshidabad District (5.538) pertaining to Krishnagar to
Berhampore section of NH-34 (New NH-12) , in the state of
West Bengal under NH(O).
Total
Length
(Kms)
41.654
48.814
43.186
50.957
41
47
17.679
Total
LOA Date - Civil
Awarded Cost
Work
(INR b)
30-03-2024
24-01-2025
25-11-2024
25-11-2024
11-02-2025
25-11-2024
30-03-2024
8.07
17.89
13.91
11.86
11.70
10.05
2.17
NH(New)
PIU
Mode
Concessionaire
DHATARWAL
CONSTRUCTION COMPANY
-PRL(JV)
Brij Gopal Construction
Pvt. Ltd.
Ashoka Buildcon Limited
R&C Infraengineers Pvt.
Limited
JSP Project Pvt Ltd.
R&C Infraengineers Pvt.
Limited
Mukherjee Associates Infra
(P) Ltd.
Mukherjee Associates Infra
(P) Ltd.
State
27
116A
116A
116A
116A
116A
12
Jalpaiguri
Kharagpur
Bardhaman
Krishnagar
Kharagpur
Krishnagar
Krishnagar
EPC
HAM
HAM
HAM
HAM
HAM
EPC
West Bengal
West Bengal
West Bengal
West Bengal
West Bengal
West Bengal
West Bengal
102
12
10.554
28-03-2024
1.10
Krishnagar
EPC
West Bengal
Source: NHAI
8 April 2025
12
 Motilal Oswal Financial Services
Sector Update | Infrastructure
NHAI focuses on asset monetization
During FY25, NHAI monetized assets worth INR287b, lower than the target of
INR390b. This shortfall is attributed to directives from the Ministry of Road
Transport and Highways (MorTH) to pause monetization through the ToT model.
Nevertheless, NHAI successfully concluded the fourth round of monetization from
NHAI InVIT raising INR177b – the highest amount ever secured through ToT mode.
For FY26, NHAI has set a monetization target of INR300b, for which it has drawn
up a tentative list of 24 road assets to be monetized with a total length of
1,472km.
Exhibit 3:
TOT bundles bid out by NHAI
Sl. no
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Bundle
TOT Bundle 1
TOT Bundle 2
TOT Bundle 3
TOT Bundle 4
TOT Bundle 5A-1
TOT Bundle 5A-2
TOT Bundle 6
TOT Bundle 7
TOT Bundle 8
TOT Bundle 9
TOT Bundle 10
TOT Bundle 11
TOT Bundle 12
TOT Bundle 13
TOT Bundle 14
TOT Bundle 15
TOT Bundle 16
Date
Aug-18
Feb-19
Nov-19
Sep-20
Jan-21
Jan-21
Mar-22
Mar-22
Mar-22
Apr-22
Apr-22
Oct-23
Oct-23
Dec-23
Dec-23
Dec-24
Sep-24
Length
682 km
586 km
566 km
401 km
54 km
106 km
108km
135km
139km
73km
125km
84km
316km
135km
138km
124km
251km
Value (INR b)
96.8
Bid cancelled
50.1
Bid cancelled
10.1
12.5
Bid cancelled
62.7
Bid cancelled
30.1
Bid cancelled
21.5
44.3
16.8
77.0
16.9
66.6
Sources: NITI Aayog, News Articles, MOFSL
FASTag toll collections continue to gain traction
FAStag toll collections improved ~15% YoY in volume terms and ~17% YoY in value
terms during 4QFY25. The daily average toll in 4QFY25 stood at ~INR2.2b per day
(+15% YoY). During FY25, FAStag toll collections increased 13% YoY.
The successful implementation of FASTag has resulted in strong toll collections on
highways. Higher toll collections play a crucial role in expediting the monetization
process of road assets by the Ministry. Additionally, toll collections benefit
companies that aim to monetize their existing toll assets.
8 April 2025
13
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Exhibit 4:
FASTag toll collections continue to improve
FASTag Toll Collections (INR b)
339
328
347
334
345
Volume (In m)
359
382
380
384
379
323 329
318
59.4
55.9
59.1
57.8
55.8
56.1
56.2
61.1
60.7
66.4
66.1
66.0
68.0
Sources: NPCI, RBI, MOFSL
Declining commodity prices to boost margins of road developers
Exhibit 5:
Domestic steel rebar price (INR/ton) declined ~25%
over Apr’22-Mar’25
Domestic Steel Rebar price (INR/ton)
Exhibit 6:
LME aluminum price (USD/MT) dipped ~18% over
Apr’22-Mar’25
LME Aluminum USD/MT
68,000
61,000 56,320
54,000
47,000
40,000
57,225
55,300
51,667
54,600
3,000
2,500 2,245
2,000
52,375
1,500
1,000
2,180
2,275
2,657
Source: MOFSL
Source: MOFSL
Exhibit 7:
Cement price (INR/50kg bag)
Cement (INR/50 kg bag)
390
360
355
330
300
270
365
348
340
354
327
338
Sources: MOFSL
8 April 2025
14
 Motilal Oswal Financial Services
Sector Update | Infrastructure
DFCCIL’s commissioning to be completed by 2025
DFCCIL has so far commissioned 2,741km of the proposed 2,843km for both the
Eastern and Western DFCs, pertaining to stretches undertaken by the
government for both corridors.
The completion deadline for the Eastern and Western DFCs has been extended
to Dec’25, primarily due to delays in land acquisition.
Exhibit 8:
Completion status of WDFC and EDFC
Section/packages
WDFC
Rewari-Palanpur
Palanpur-Makarpura
Makarpura-Sachin
Sachin-Vaitarna
Vaitarna-JNPT
Dadri-Rewari
EDFC
Bhaupur-Khurja
Bhaupur-DDU
DDU -Sonnagar
Khurja-Dadri
Pilkhani–Ludhiana
Khurja-Pilkhani
351km
402km
137km
46km
179km
222km
Commissioned
Commissioned
Commissioned
Commissioned
Commissioned
Commissioned
Sources: DFCCIL, MOFSL
96%
Rewari-Madar
Madar-Palanpur
306km
353km
290km
135km
186km
102km
127km
Commissioned
Commissioned
Commissioned
Commissioned
Commissioned
Dec’25
Commissioned
93%
Length
Commissioning target
Financial
progress
8 April 2025
15
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Exhibit 9:
Completion status of WDFC and EDFC – Map view
Sources: DFCCIL, MOFSL
Exhibit 10:
GoI has budgeted to spend ~INR10.2t in capex in FY25
Sl.
no
1
2
3
4
5
Ministry
Road transport and highways
Railways
Housing & urban affairs
Ports, shipping, and waterways
Others
Total
FY25 budget
capex estimates
(revised, INR b)
2,725
2,520
317
13.4
4,609
10,184
Actual capex
% of actual capex in
in Apr’24-Feb'25
Apr’24-Feb’25
(INR b)
to BE
2,413
88.6
2,293
91.0
280
88.3
12.9
96.3
3,120
67.7
8,119
79.7
Sources: Controller General of Accounts, MOFSL
Investment in securities market are subject to market risks. Read all the related documents carefully before investing.
8 April 2025
16
 Motilal Oswal Financial Services
Sector Update | Infrastructure
Explanation of Investment Rating
Investment Rating
BUY
SELL
NEUTRAL
UNDER REVIEW
NOT RATED
Expected return (over 12-month)
>=15%
< - 10%
< - 10 % to 15%
Rating may undergo a change
We have forward looking estimates for the stock but we refrain from assigning recommendation
-
*In case the recommendation given by the Research Analyst is inconsistent with the investment rating legend for a continuous period of 30 days, the Research Analyst shall be within following 30 days take
appropriate measures to make the recommendation consistent with the investment rating legend.
Disclosures
The following Disclosures are being made in compliance with the SEBI Research Analyst Regulations 2014 (herein after referred to as the Regulations).
Motilal Oswal Financial Services Ltd. (MOFSL) is a SEBI Registered Research Analyst having registration no. INH000000412. MOFSL, the Research Entity (RE) as defined in the Regulations, is engaged in
the business of providing Stock broking services, Depository participant services & distribution of various financial products. MOFSL is a listed public company, the details in respect of which are available on
www.motilaloswal.com. MOFSL (erstwhile Motilal Oswal Securities Limited - MOSL) is registered with the Securities & Exchange Board of India (SEBI) and is a registered Trading Member with National Stock
Exchange of India Ltd. (NSE) and Bombay Stock Exchange Limited (BSE), Multi Commodity Exchange of India Limited (MCX) and National Commodity & Derivatives Exchange Limited (NCDEX) for its stock
broking activities & is Depository participant with Central Depository Services Limited (CDSL) National Securities Depository Limited (NSDL),NERL, COMRIS and CCRL and is member of Association of
Mutual Funds of India (AMFI) for distribution of financial products and Insurance Regulatory & Development Authority of India (IRDA) as Corporate Agent for insurance products. Details of associate entities
of Motilal Oswal Financial Services Limited are available on the website at http://onlinereports.motilaloswal.com/Dormant/documents/List%20of%20Associate%20companies.pdf
MOFSL and its associate company(ies), their directors and Research Analyst and their relatives may; (a) from time to time, have a long or short position in, act as principal in, and buy or sell the securities or
derivatives thereof of companies mentioned herein. (b) be engaged in any other transaction involving such securities and earn brokerage or other compensation or act as a market maker in the financial
instruments of the company(ies) discussed herein or act as an advisor or lender/borrower to such company(ies) or may have any other potential conflict of interests with respect to any recommendation and
other related information and opinions.; however the same shall have no bearing whatsoever on the specific recommendations made by the analyst(s), as the recommendations made by the analyst(s) are
completely independent of the views of the associates of MOFSL even though there might exist an inherent conflict of interest in some of the stocks mentioned in the research report.
MOFSL and / or its affiliates do and seek to do business including investment banking with companies covered in its research reports. As a result, the recipients of this report should be aware that MOFSL
may have a potential conflict of interest that may affect the objectivity of this report. Compensation of Research Analysts is not based on any specific merchant banking, investment banking or brokerage
service
transactions.
Details
of
pending
Enquiry
Proceedings
of
Motilal
Oswal
Financial
Services
Limited
are
available
on
the
website
at
https://galaxy.motilaloswal.com/ResearchAnalyst/PublishViewLitigation.aspx
A graph of daily closing prices of securities is available at www.nseindia.com, www.bseindia.com. Research Analyst views on Subject Company may vary based on Fundamental research and Technical
Research. Proprietary trading desk of MOFSL or its associates maintains arm’s length distance with Research Team as all the activities are segregated from MOFSL research activity and therefore it can have
an independent view with regards to Subject Company for which Research Team have expressed their views.
Regional Disclosures (outside India)
This report is not directed or intended for distribution to or use by any person or entity resident in a state, country or any jurisdiction, where such distribution, publication, availability or use would be contrary
to law, regulation or which would subject MOFSL & its group companies to registration or licensing requirements within such jurisdictions.
For Hong Kong:
This report is distributed in Hong Kong by Motilal Oswal capital Markets (Hong Kong) Private Limited, a licensed corporation (CE AYY-301) licensed and regulated by the Hong Kong Securities and Futures
Commission (SFC) pursuant to the Securities and Futures Ordinance (Chapter 571 of the Laws of Hong Kong) “SFO”. As per SEBI (Research Analyst Regulations) 2014 Motilal Oswal Securities (SEBI Reg.
No. INH000000412) has an agreement with Motilal Oswal capital Markets (Hong Kong) Private Limited for distribution of research report in Hong Kong. This report is intended for distribution only to “Professional
Investors” as defined in Part I of Schedule 1 to SFO. Any investment or investment activity to which this document relates is only available to professional investor and will be engaged only with professional
investors.” Nothing here is an offer or solicitation of these securities, products and services in any jurisdiction where their offer or sale is not qualified or exempt from registration. The Indian Analyst(s) who
compile this report is/are not located in Hong Kong & are not conducting Research Analysis in Hong Kong.
For U.S.
Motilal Oswal Financial Services Limited (MOFSL) is not a registered broker - dealer under the U.S. Securities Exchange Act of 1934, as amended (the"1934 act") and under applicable state laws in the United
States. In addition MOFSL is not a registered investment adviser under the U.S. Investment Advisers Act of 1940, as amended (the "Advisers Act" and together with the 1934 Act, the "Acts), and under
applicable state laws in the United States. Accordingly, in the absence of specific exemption under the Acts, any brokerage and investment services provided by MOFSL, including the products and services
described herein are not available to or intended for U.S. persons. This report is intended for distribution only to "Major Institutional Investors" as defined by Rule 15a-6(b)(4) of the Exchange Act and
interpretations thereof by SEC (henceforth referred to as "major institutional investors"). This document must not be acted on or relied on by persons who are not major institutional investors. Any investment
or investment activity to which this document relates is only available to major institutional investors and will be engaged in only with major institutional investors. In reliance on the exemption from registration
provided by Rule 15a-6 of the U.S. Securities Exchange Act of 1934, as amended (the "Exchange Act") and interpretations thereof by the U.S. Securities and Exchange Commission ("SEC") in order to conduct
business with Institutional Investors based in the U.S., MOFSL has entered into a chaperoning agreement with a U.S. registered broker-dealer, Motilal Oswal Securities International Private Limited. ("MOSIPL").
Any business interaction pursuant to this report will have to be executed within the provisions of this chaperoning agreement.
The Research Analysts contributing to the report may not be registered /qualified as research analyst with FINRA. Such research analyst may not be associated persons of the U.S. registered broker-dealer,
MOSIPL, and therefore, may not be subject to NASD rule 2711 and NYSE Rule 472 restrictions on communication with a subject company, public appearances and trading securities held by a research
analyst account.
For Singapore
In Singapore, this report is being distributed by Motilal Oswal Capital Markets (Singapore) Pte. Ltd. (“MOCMSPL”) (UEN 201129401Z), which is a holder of a capital markets services license and an exempt
financial adviser in Singapore.This report is distributed solely to persons who (a) qualify as “institutional investors” as defined in section 4A(1)(c) of the Securities and Futures Act of Singapore (“SFA”) or (b)
are considered "accredited investors" as defined in section 2(1) of the Financial Advisers Regulations of Singapore read with section 4A(1)(a) of the SFA. Accordingly, if a recipient is neither an “institutional
investor” nor an “accredited investor”, they must immediately discontinue any use of this Report and inform MOCMSPL .
In respect of any matter arising from or in connection with the research you could contact the following representatives of MOCMSPL. In case of grievances for any of the services rendered by MOCMSPL
write to grievances@motilaloswal.com.
Nainesh Rajani
Email: nainesh.rajani@motilaloswal.com
Contact: (+65) 8328 0276
.
Specific Disclosures
1. Research Analyst and/or his/her relatives do not have a financial interest in the subject company(ies), as they do not have equity holdings in the subject company(ies).
MOFSL has financial interest in the subject company(ies) at the end of the week immediately preceding the date of publication of the Research Report: No.
Nature of Financial interest is holding equity shares or derivatives of the subject company
2. Research Analyst and/or his/her relatives do not have actual/beneficial ownership of 1% or more securities in the subject company(ies) at the end of the month immediately
preceding the date of publication of Research Report.
MOFSL has actual/beneficial ownership of 1% or more securities of the subject company(ies) at the end of the month immediately preceding the date of publication of Research
Report:No
3. Research Analyst and/or his/her relatives have not received compensation/other benefits from the subject company(ies) in the past 12 months.
MOFSL may have received compensation from the subject company(ies) in the past 12 months.
4. Research Analyst and/or his/her relatives do not have material conflict of interest in the subject company at the time of publication of research report.
MOFSL does not have material conflict of interest in the subject company at the time of publication of research report.
5. Research Analyst has not served as an officer, director or employee of subject company(ies).
6. MOFSL has not acted as a manager or co-manager of public offering of securities of the subject company in past 12 months.
7. MOFSL has not received compensation for investment banking /merchant banking/brokerage services from the subject company(ies) in the past 12 months.
8. MOFSL may have received any compensation for products or services other than investment banking or merchant banking or brokerage services from the subject company(ies)
in the past 12 months.
9. MOFSL may have received compensation or other benefits from the subject company(ies) or third party in connection with the research report.
10. MOFSL has not engaged in market making activity for the subject company.
********************************************************************************************************************************
The associates of MOFSL may have:
financial interest in the subject company
8 April 2025
17
 Motilal Oswal Financial Services
Sector Update | Infrastructure
-
-
-
-
-
-
-
actual/beneficial ownership of 1% or more securities in the subject company at the end of the month immediately preceding the date of publication of the Research Report or date of the public appearance.
received compensation/other benefits from the subject company in the past 12 months
any other potential conflict of interests with respect to any recommendation and other related information and opinions.; however the same shall have no bearing whatsoever on the specific recommendations
made by the analyst(s), as the recommendations made by the analyst(s) are completely independent of the views of the associates of MOFSL even though there might exist an inherent conflict of interest in
some of the stocks mentioned in the research report.
acted as a manager or co-manager of public offering of securities of the subject company in past 12 months
be engaged in any other transaction involving such securities and earn brokerage or other compensation or act as a market mak er in the financial instruments of the company(ies) discussed herein or act as
an advisor or lender/borrower to such company(ies)
received compensation from the subject company in the past 12 months for investment banking / merchant banking / brokerage services or from other than said services.
Served subject company as its clients during twelve months preceding the date of distribution of the research report.
The associates of MOFSL has not received any compensation or other benefits from third party in connection with the research report
Above disclosures include beneficial holdings lying in demat account of MOFSL which are opened for proprietary investments only. While calculating beneficial holdings, It does not consider demat accounts
which are opened in name of MOFSL for other purposes (i.e holding client securities, collaterals, error trades etc.). MOFSL also earns DP income from clients which are not considered in above disclosures.
Analyst Certification
The views expressed in this research report accurately reflect the personal views of the analyst(s) about the subject securities or issues, and no part of the compensation of the research analyst(s) was, is, or
will be directly or indirectly related to the specific recommendations and views expressed by research analyst(s) in this report.
Terms & Conditions:
This report has been prepared by MOFSL and is meant for sole use by the recipient and not for circulation. The report and information contained herein is strictly confidential and may not be altered in any
way, transmitted to, copied or distributed, in part or in whole, to any other person or to the media or reproduced in any form, without prior written consent of MOFSL. The report is based on the facts, figures
and information that are considered true, correct, reliable and accurate. The intent of this report is not recommendatory in nature. The information is obtained from publicly available media or other sources
believed to be reliable. Such information has not been independently verified and no guaranty, representation of warranty, express or implied, is made as to its accuracy, completeness or correctness. All such
information and opinions are subject to change without notice. The report is prepared solely for informational purpose and does not constitute an offer document or solicitation of offer to buy or sell or subscribe
for securities or other financial instruments for the clients. Though disseminated to all the customers simultaneously, not all customers may receive this report at the same time. MOFSL will not treat recipients
as customers by virtue of their receiving this report.
Disclaimer:
The report and information contained herein is strictly confidential and meant solely for the selected recipient and may not be altered in any way, transmitted to, copied or distributed, in part or in whole, to any
other person or to the media or reproduced in any form, without prior written consent. This report and information herein is solely for informational purpose and may not be used or considered as an offer
document or solicitation of offer to buy or sell or subscribe for securities or other financial instruments. Nothing in this report constitutes investment, legal, accounting and tax advice or a representation that
any investment or strategy is suitable or appropriate to your specific circumstances. The securities discussed and opinions expressed in this report may not be suitable for all investors, who must make their
own investment decisions, based on their own investment objectives, financial positions and needs of specific recipient. This may not be taken in substitution for the exercise of independent judgment by any
recipient. Each recipient of this document should make such investigations as it deems necessary to arrive at an independent evaluation of an investment in the securities of companies referred to in this
document (including the merits and risks involved), and should consult its own advisors to determine the merits and risks of such an investment. The investment discussed or views expressed may not be
suitable for all investors. Certain transactions -including those involving futures, options, another derivative products as well as non-investment grade securities - involve substantial risk and are not suitable
for all investors. No representation or warranty, express or implied, is made as to the accuracy, completeness or fairness of the information and opinions contained in this document. The Disclosures of Interest
Statement incorporated in this document is provided solely to enhance the transparency and should not be treated as endorsement of the views expressed in the report. This information is subject to change
without any prior notice. The Company reserves the right to make modifications and alternations to this statement as may be required from time to time without any prior approval. MOFSL, its associates, their
directors and the employees may from time to time, effect or have effected an own account transaction in, or deal as principal or agent in or for the securities mentioned in this document. They may perform
or seek to perform investment banking or other services for, or solicit investment banking or other business from, any company referred to in this report. Each of these entities functions as a separate, distinct
and independent of each other. The recipient should take this into account before interpreting the document. This report has been prepared on the basis of information that is already available in publicly
accessible media or developed through analysis of MOFSL. The views expressed are those of the analyst, and the Company may or may not subscribe to all the views expressed therein. This document is
being supplied to you solely for your information and may not be reproduced, redistributed or passed on, directly or indirectly, to any other person or published, copied, in whole or in part, for any purpose. This
report is not directed or intended for distribution to, or use by, any person or entity who is a citizen or resident of or located in any locality, state, country or other jurisdiction, where such distribution, publication,
availability or use would be contrary to law, regulation or which would subject MOFSL to any registration or licensing requirement within such jurisdiction. The securities described herein may or may not be
eligible for sale in all jurisdictions or to certain category of investors. Persons in whose possession this document may come are required to inform themselves of and to observe such restriction. Neither the
Firm, not its directors, employees, agents or representatives shall be liable for any damages whether direct or indirect, incidental, special or consequential including lost revenue or lost profits that may arise
from or in connection with the use of the information. The person accessing this information specifically agrees to exempt MOFSL or any of its affiliates or employees from, any and all responsibility/liability
arising from such misuse and agrees not to hold MOFSL or any of its affiliates or employees responsible for any such misuse and further agrees to hold MOFSL or any of its affiliates or employees free and
harmless from all losses, costs, damages, expenses that may be suffered by the person accessing this information due to any errors and delays.
This report is meant for the clients of Motilal Oswal only.
Investment in securities market are subject to market risks. Read all the related documents carefully before investing.
Registration granted by SEBI and certification from NISM in no way guarantee performance of the intermediary or provide any assurance of returns to investors.
Registered Office Address: Motilal Oswal Tower, Rahimtullah Sayani Road, Opposite Parel ST Depot, Prabhadevi, Mumbai-400025; Tel No.: 022 - 71934200 / 71934263; www.motilaloswal.com.
Correspondence Address: Palm Spring Centre, 2nd Floor, Palm Court Complex, New Link Road, Malad (West), Mumbai- 400 064. Tel No: 022 71881000. Details of Compliance Officer: Neeraj Agarwal,
Email Id: na@motilaloswal.com, Contact No.:022-40548085.
Grievance Redressal Cell:
Contact Person
Ms. Hemangi Date
Ms. Kumud Upadhyay
Mr. Ajay Menon
Contact No.
022 40548000 / 022 67490600
022 40548082
022 40548083
Email ID
query@motilaloswal.com
servicehead@motilaloswal.com
am@motilaloswal.com
Registration details of group entities.: Motilal Oswal Financial Services Ltd. (MOFSL): INZ000158836 (BSE/NSE/MCX/NCDEX); CDSL and NSDL: IN-DP-16-2015; Research Analyst: INH000000412 . AMFI:
ARN .: 146822. IRDA Corporate Agent – CA0579. Motilal Oswal Financial Services Ltd. is a distributor of Mutual Funds, PMS, Fixed Deposit, Insurance, Bond, NCDs and IPO products.
Customer having any query/feedback/ clarification may write to query@motilaloswal.com. In case of grievances for any of the services rendered by Motilal Oswal Financial Services Limited (MOFSL) write to
grievances@motilaloswal.com, for DP to dpgrievances@motilaloswal.com.
8 April 2025
18